PROJECT NAME: OR99E: Clackamas River (McLoughlin) Bridge
STIP ID NUMBER: 20472
BRIDGE NUMBER: 01617
MILE POINT: 11.2
ISSUE: Bridge is starting to deteriorate and is in need of paint.
PURPOSE AND NEED:If distresses are not addressed in a timely manner, it will be hard to catch up due to the size of the bridge. Deteriorating conditions could lead to mobility impacts.
PROPOSED SOLUTION: Design shelf ready plans to paint the structure
TOTAL COST: $250,000
Note: This project was selected to be part of the ODOT shelf program. The allocated funding pays for the design phase of the project. This approach allows ODOT to have shovel ready projects to be constructed once additional funding is available.