PROJECT NAME: OR99W: Tualatin River Bridge
STIP ID NUMBER: 20471
BRIDGE NUMBER: 01417N
MILE POINT: 12.18
ISSUE: Some areas in spans 1 and 2 have dense cracking, other areas of spans 1 and 2 have large cracks. There are cracks with rust staining in the soffit of all spans in the negative moment areas. The joints are leaking.
PURPOSE AND NEED: The cracks in the overlay allow water to penetrate and may accelerate any debonding between the deck and the overlay.
PROPOSED SOLUTION: Design shelf ready plans to replace the current structural overlay
TOTAL COST: $188,500
Note: This project was selected to be part of the ODOT shelf program. The allocated funding pays for the design phase of the project. This approach allows ODOT to have shovel ready projects that will be ready to go to construction once additional funding is available.